Geotechnics

Superstructure of Schleyerhofweg landfill site

Project details

  • Services: Preliminary investigation of the contaminated site and cost estimate for purchase, subsoil investigation by means of deep drilling and foundation recommendation for multi-storey office building, waterproofing planning incl. coordination with authorities, expert monitoring and external inspection of the waterproofing construction.
  • Term: 2018 - 2022
  • Industry of the client: Area revitalisation
  • Special features: Old landfill is located in water protection zone IIIB (special requirements for material placement).